FOOTPRINTS OF IFFCO PHULPUR UNIT

IFFCO PHULPUR UNIT

S.No.

Description

Date

1

Foundation Stone laying of IFFCO Phulpur by Prime Minister Mrs. Indira Gandhi

16 Jan. 1974

2

Start of Phulpur-I Project

26 May. 1976

3

Start of Civil Erection Work of Phulpur-I

Dec. 1976

4

Start of Mechanical Erection Work of Phulpur-I

Dec., 1977

5

Phulpur-I Ammonia Plant Start

10 Oct.,1980

6

Phulpur-I Urea Plant Start

15 Oct., 1980

7

Phulpur-I Commercial Production start

28 Mar., 1981

8

Dedication of Phulpur Plant to the Nation of Prime Minister Mrs. Indira Gandhi

30 Dec., 1981

9

Commissioning of Phulpur-I PGR plant

20 July, 1985

10

Phulpur-I Ammonia plant Synthesis Converter retrofit (switching to axial radial flow , CASALE’s revamp)

17 June, 1993

11

Replacement of CO2 Compressor Turbine in Urea-I plant

15 June, 1993

12

Installation of 2nd Ammonia Storage Tank (5000 MT)

Oct., 1993

13

Start of Phulpur-II Project (Zero date of the Project)

20 Apr, 1995

14

Start of Civil & Mechanical Erection work of Phulpur-II

June, 1995

15

Phulpur-I Ammonia plant CO2 removal system retrofitting to Lo Heat Benfield system

20 June, 1995

16

Phulpur-II Bagging Plant Commissioning

14 Aug., 1997

17

Phulpur-II Urea plant (Stream-31) start

18 Oct., 1997

18

Phulpur-II Urea plant (Stream-41) start

8 Dec., 1997

19

Phulpur-II Ammonia plant start

18 Dec., 1997

20

Phulpur-II Commercial Production start

22 Dec., 1997

21

Commissioning of Reverse Osmosis (RO) Plant for effluent treatment

June, 1998

22

Up gradation of Instrumentation System from Pneumatic to DCS (Centum CS) in Ammonia-I, Urea-I and Power Plant

30 Apr.,2000

23

Installation  of Pre concentrator  in Urea-I plant

28 Apr.,2001

24

Installation  of PGR in Ammonia-II plant

Dec., 2001

25

Agreement of R-LNG supply with M/s GAIL India Ltd.

25 Aug., 2004

26

Energy Saving Project (Phase-I) in Ammonia-II Plant

April, 2005

27

Energy Saving Project (Phase-I) in Ammonia-I Plant

May, 2005

28

Energy Saving Project (Phase-II) in Ammonia-II Plant

March, 2006

29

Energy Saving Project (Phase-II) in Ammonia-I Plant

July, 2006

30

R-LNG Conversion in Ammonia-II and Boiler No. 4

April, 2006

31

R-LNG Conversion in Ammonia-I

June, 2006

32

R-LNG Conversion in Boilers 1,2 & 3

July, 2006

33

Installation of Carbon Di Oxide Recovery (CDR) plant in Ammonia-II plant

16 Dec., 2006

34

Capacity Enhancement Project in Ammonia-I Plant

Nov., 2008

35

Capacity Enhancement Project in Urea-I Plant

Nov., 2008

36

Capacity Enhancement Project in Ammonia-II Plant

Dec., 2008

37

Capacity Enhancement Project in Urea-II Plant

Dec., 2008

38

Start of commercial production of  Neem coated urea  in Phulpur Unit-I

4 Aug.,2011

39

Installation of New Membrane based PGR Unit in Ammonia-I

11 April 2013

40

Ammonia Converter (S-50) Cold shell Modification in Ammonia-II plant

6 April 2014

41

Start of commercial production of  Neem coated urea  in Phulpur Unit-II

4 Dec.,2014

42

Installation of 235 kWp Solar power Plant at the roof of Raw water Storage Tank

24 Jan., 2016

43

Installation of 350 kWp Solar power Plant at the roof of Raw water Storage Tank

19 Feb., 2016

44

Energy Saving Project in Ammonia-II Plant (Phase-1)

7 May, 2016

45

Commissioning of New GTG–HRSG

14 Nov., 2016

46

Energy Saving Project in Urea-I Plan

15 Dec., 2016

47

Energy Saving Project in Urea-II Plant (Phase-1)

8 Jan., 2017

48

Energy Saving Project in Ammonia-I Plant

4 Feb., 2017

49

Installation of Dry gas seals in Refrigeration Compressor (105-J) in Ammonia-I plant

4 Feb., 2017

50

Neem Oil extraction plant commissioned at CORDET

17 Feb., 2017

51

Energy Saving Project in Ammonia-II & Urea-II Plant (Phase-2):

5 Jul., 2017